Excavation dewatering

Excavation dewatering

We carry out complete dewatering works on construction sites — from choosing the method, through installing the system, to running it for as long as the works last.

Dewatering an excavation means removing groundwater and rainwater from the working area and holding the water table below the excavation floor. Without it the floor turns to slurry, the slopes lose stability, and concreting or pipe laying has to stop. A well-designed dewatering scheme is usually not an extra cost — it shortens the build and removes standstills.

We dewater excavations for gas pipelines, sanitary sewers, separators, pumping stations, pipe-jacking and drilling pits, and foundations. We have experience on large projects — power station blocks, gas pipelines up to DN 1000, expressways, weirs and hydroelectric plants — and on smaller investments: residential construction and sewer works.

We run several dozen of our own wellpoint pumps with electric and diesel drives, including sound-insulated units, as well as submersible pumps and motor pumps. As standard we use 32 mm wellpoints (7 m long) and 50 mm wellpoints (4–6 m); larger diameters, up to 100 mm, are possible. We have support equipment — mini-excavators, drilling rigs, tanks and settling tanks for the discharge — and our own transport, and on large jobs we work with a Dutch dewatering company that can supply extra pumps and equipment when needed.

We match the method and the equipment to the ground and water conditions of the particular site — not the other way round. If you only need the equipment, we also offer wellpoint and pump rental.

What we do

  • Wellpoint systems (deep dewatering)
  • Direct pumping from the excavation
  • Deep wells
  • Deep and multi-stage dewatering
  • Site and foundation dewatering
Wellpoint installation around a construction excavation — Promopol dewatering
Wellpoint diameters
32–100 mm
Coverage
all of Poland
Fleet
our own

A question about scope or timing?

Describe your site to us — we will tell you plainly whether and how we can help.

Methods

Dewatering methods — which one to choose

The choice comes down to the ground and water conditions, the depth of the excavation and how long the works run. Below, briefly, where each method fits.

01

Wellpoints

When: ground from sandy gravels down to fine and silty sands, trench and structure excavations

The most common deep dewatering method. Wellpoints are jetted into the ground along the excavation and joined by a suction header to a pump unit. One stage of wellpoints typically lowers the water table by about 4–5 m — no more than 5–6 m, because suction lift sets the limit; deeper excavations use further stages.

02

Deep wells

When: deep excavations, highly permeable soils, large water inflow

Drilled wells fitted with submersible pumps create a cone of depression covering the whole working area. Chosen where wellpoints cannot reach the required depth or the inflow is too great.

03

Direct pumping

When: small inflow, cohesive soils, short works

Water is collected in sumps at the bottom of the excavation and pumped out with submersible pumps. The simplest and cheapest method, but in loose soils it risks carrying away soil particles and undermining the excavation floor.

How the work runs

How dewatering is carried out

Every site is different, but the order of work in wellpoint dewatering is usually the same.

  1. 01

    Site assessment

    We start by talking about the site: excavation depth, the level the water must be lowered to, the type of ground and the timetable. If there is a geotechnical survey, we base the design on it.

  2. 02

    Method and equipment

    On that basis we choose the method — wellpoints, deep wells or direct pumping — and the number of pumps, the drive and the length of the installation.

  3. 03

    Installation

    Wellpoints are jetted into the ground along the excavation and connected to a suction header, and the header to the pump unit. A delivery pipe carries the water to the agreed discharge point.

  4. 04

    Lowering the water table

    Pumping starts ahead of time, so the water is down before the works go below its level. How long that takes depends on the ground and the amount of water.

  5. 05

    Continuous running

    The installation runs 24 hours a day for as long as work continues below the water table — a break means the water rises in the excavation again.

  6. 06

    Removal

    Once the work below the water table is finished and the excavation backfilled, we dismantle the installation and take the equipment away.

Risks

What to watch for

Dewatering changes the water conditions not only in the excavation but around it. We go through these points before we start.

Neighbouring buildings

Lowering the water table changes conditions in the ground beyond the excavation too. In compressible soils this can cause settlement of nearby buildings and utilities, so the extent and duration of dewatering are planned with the neighbourhood in mind.

Loss of fines

A poorly chosen filter, or direct pumping in loose soils, carries fine soil particles out with the water. The ground loosens and the excavation floor can be disturbed — which is why choosing the wellpoints is not a formality.

Interruptions

When the pumps stop, the water comes back into the excavation, often very quickly, and with water under pressure below the floor it can heave the base. On mains power, have a plan for a supply failure — a diesel-driven pump on standby, for example.

Discharge

The pumped water has to go somewhere — a storm sewer, a ditch or a watercourse. Discharge is agreed with whoever manages it, and settling tanks are used when the water carries suspended solids.

Paperwork

Notification or water-law permit

Under the Polish Water Law (consolidated text: Dz.U. 2025 item 960), permanent dewatering of construction excavations and the discharge of water from excavations require a water-law notification, zgłoszenie wodnoprawne (art. 394(1) points 5 and 8). It is filed with the water supervision office of Wody Polskie before the works begin, and the works may start if the authority raises no objection within 30 days of receiving it (art. 423(2)).

A water-law permit, pozwolenie wodnoprawne, is required among other things for long-term lowering of the groundwater table (art. 389 point 3). The often-quoted test of whether the cone of depression stays within the plot comes from the act in force until the end of 2017 — for excavations the current rules do not use it.

A notification does not replace approvals required under other rules (art. 423(2)). If the water is to go into someone else's water facility, such as a ditch, the owner's consent is attached to the notification (art. 422 point 4). This is a summary of the rules, not legal advice — in a particular case the dewatering design and the authority decide.

Before you call

What is worth having ready

The more of this you can give us straight away, the sooner you get a specific answer instead of a general one.

  1. 01Site location and the planned schedule of works
  2. 02Excavation depth and the level the water must be lowered to
  3. 03Soil type — geotechnical investigation or documentation, if you have it
  4. 04Length or area to be dewatered
  5. 05Power available on site (400 V) or the need for a diesel drive
  6. 06Where the pumped water can be discharged
Frequent questions

Questions and answers

When is dewatering an excavation necessary?
Whenever the excavation floor sits below the groundwater table. On site you see it as water seeping from the slopes, a soft, “pumping” floor, and slumping excavation walls. In those conditions foundation works and pipe laying cannot be carried out safely.
How far can wellpoints lower the groundwater?
One stage of wellpoints typically lowers the water table by about 4–5 m below the level the pump stands at — at most 5–6 m, because suction lift allows no more. Deeper excavations use further stages of the installation or deep wells. The actual figure depends on the soil type and its permeability.
How much does dewatering an excavation cost?
We do not publish a price list, because every site is different — the cost depends on the method, the length of the installation, the running time, the type of drive and transport. We give a specific quote after talking through the conditions on site. Prepare the information listed above and you will have it sooner.
Do the pumps run without stopping?
Yes. A dewatering installation has to run continuously for as long as work goes on below the water table — a break means the water rises in the excavation again. Our piston pumps are built to run 24 hours a day.
Do you serve sites across the whole of Poland?
Yes. Our equipment yard is in Opole, but we have worked in every voivodeship. Transport of the equipment to site and its collection are arranged for a fee — with our own transport or through a forwarding company.
Can wellpoints pump out a flooded excavation?
Wellpoints lower the groundwater around the excavation — ideally before the works go below the water table. Water already standing in the excavation, rainwater for instance, is removed with submersible pumps; after that the wellpoint installation keeps the excavation dry.
How long does it take to lower the water level?
It depends on the ground, the depth and the amount of water: in permeable ground the water table drops faster, in fine-grained soils more slowly. That is why pumping starts ahead of time, before the works go below the water level.
Does excavation dewatering need a water-law permit?
As a rule a water-law notification is enough: permanent dewatering of construction excavations and discharging water from them require one (art. 394(1) points 5 and 8 of the Water Law). A permit is needed among other things for long-term lowering of the groundwater table (art. 389 point 3). More in the paperwork section above.